Tuki Street - Full Concrete Package Delivered in 7 Days

Tuki Street

Clients: Wellington Contractors
Location: Titahi Bay
Contractors: A&B Concrete

Project Overview

A&B Concrete was engaged to deliver the complete concrete package for the Tuki Street development. The full scope was delivered within just 7 days from initial engagement to completion demonstrating rapid mobilisation, strong coordination, and efficient execution. 

  • 221m² of exposed aggregate footpaths
  • 427m² of light broom-finished concrete surfaces

Challenges

  • Tight programme requiring rapid mobilisation and completion
  • Restricted site access requiring careful machinery coordination and sequencing

Scope of Works

  • Site establishment and preparation
  • Formwork assembly and dismantling
  • Driveway protection (polythene installation)
  • Supply and placement of reinforcing
  • Supply of 30MPa concrete
  • Concrete pumping to designated areas
  • Placement of exposed aggregate and broom finish surfaces
  • Saw cutting for control joints
  • Final finishing and clean-up

Outcome

  • Delivered on time
  • High-quality exposed and broom finishes
  • Zero programme overrun
  • Strong client satisfaction
  • Demonstrated capability to manage a full concrete package from start to finish